President of Russia Visits Krasnodarskaya CHPP
OREANDA-NEWS. October 20, 2011. During his trip to
Accompanied by President of OAO LUKOIL Vagit Alekperov and Krasnodar Territory Governor Alexander Tkachev, the President of Russia inspected a new 410 MW combined-cycle gas turbine (CCGT-410).
The CCGT-410 construction has been completed. The turbine is being prepared for start-up.
The new unit will increase the installed electric capacity of Krasnodarskaya CHPP by 50% to 1,090 MW.
The efficiency factor of CCGT-410 is 57%, which is 1.5-times higher compared to the existing steam turbine units installed at the vast majority of Russian thermal power plants (TPP) and combined heat power plants. The new turbine consumes 350 million cubic meters per year less natural gas than conventional steam turbine units with a similar capacity.
State-of-the-art natural gas combustion technologies used by CCGT-410 reduce NOx emissions to 50 mg per cubic meter or less, which is considerably lower than emissions from typical steam boilers.
CCGT-410 will cover up to 10-15% of electric load in the region and improve energy supply reliability in
CCGT-410 is the second project implemented by LUKOIL in the south of