Essar Steel India Successfully Commissions Corex Module
OREANDA-NEWS. October 14, 2011. Essar Steel has successfully commissioned a Corex module, with a capacity of 0.87 MTPA, as part of its expansion programe for increasing steel production capacity from 4.6 MTPA to 10 MTPA at its Hazira complex. It has earlier commissioned Blast furnace and a DRI module. With this the iron making capacity has reached over 9.5 MTPA. A second Corex module of 0.87 MTPA is expected to be commissioned shortly. The overall expansion including downstream facilities at Hazira is being done at a cost Rs.17,000 crores.
The first tap of Hot metal from Corex was successfully converted into saleable product, which is a remarkable achievement.
Highlights of the Essar's Corex facility can be summarized as follows:
Significant lower investment costs and operating costs vis-a-vis blast furnace
Outstanding environmental compatibility
Highest operational flexibility, i.e., production output and diversifying energy needs
Use of Corex export gas for many applications within the plant
Essar Steel Hazira complex is thus poised to become
The recently installed state of the art Compact Strip plant, Plate mill along with steel making capability allows us to produce high quality value added products to serve both the domestic and export markets.
Major facilities are expected to be commissioned by March 2012.