OREANDA-NEWS. October 12, 2011. Supply of hot water and heat to residential premises of Ust-Ilimsk has been fully recovered, works at heating system manifolds were carried out by managing companies in cooperation with experts of Ust-Ilimskaya CHPP. Visits to apartments with damaged heating units are being completed jointly with managing companies. After due evaluation of the consequences of the accident, OAO Irkutskenergo will reimburse the costs of purchase and installation of heating units incurred by residents.

Ad hoc commission of Ust-Ilimskaya CHPP is investigating the cause of yesterday’s hydraulic control violation at the pumping facilities of Novy Gorod CHPP heating main, which resulted in violation of hydraulic control in the right-bank district of Ust-Ilimsk.