Perm CHPP-6 Installed Siemens Gas Turbines and Distribution Facility
OREANDA-NEWS. August 17, 2011. The “Malakhit” Investment project of IES Holding is at the final stage.
At the end of May, 2011 the installation of Siemens gas turbines SGT-800 and ancillary equipment on a construction site of the combined cycle unit (CCU) of Perm CHPP-6 was completed. Currently the mechanical verification testing of turbines as well as checking of the system facilities according to equipment and instrumentation arrangement drawings are in progress. Due to the completed installation of gas turbines the installation of waste heat boilers moved to a final stage.
At the beginning of June there was completed an installation of an integrated distribution unit with hexafluorated sulfur insulation (KRUE). This system implements a critical function of receiving power from a power unit and distributing it for further transfer by means of a power network.
KRUE installed at the CCU of Perm CHPP-6 is distinguished by multifunctional performance – a single frame includes collecting buses, a switch, disconnectors with grounding switches, current transformers which allow to reduce dimensions materially and increase the reliability of ODU (open distribution unit) of the power unit. It should be also outlined that the KRUE building is equipped with a contemporary lightning, fire protection and fire-fighting systems.
The reconstruction of Perm CHPP-6 is a part of “Malakhit” project which is included in the “Diadema” investment program of CJSC “Integrated Energy Systems”. “Malakhit” project is a priority one for the company and is critical for the development of energy system of
The "Malakhit" project will result in triple increase of the electrical power capacity of the plant – to 180 MW, the heating capacity – by 240 Gcal/h to 833 Gcal/h. The installed heating capacity will additionally provide heat to 50 thousand flats. Hence the city center of