Azerenergy Reports on Repair Work
OREANDA-NEWS. August 15, 2011. The collective of “Mingachevir Electric Network” is achieved successful results in the end of half year as last months of the current year. So that, the payment under local private consumer group was 100,3 % and total payment was 101,7 % in accordance to 6 months result of 2011, taking into account of the debtor debts of last months, reported the press-centre of Azerenergy.
The information about carried out repair work was noted in the information given by the enterprise to the Press – release of “Azerenergy” JSC.
As the source informed, cutting process was implemented at the trees can be the result of accidents during the mentioned period. TL number 18, 24 and 23 by 6 kV and “Baghlar” TL number 25 were cleaned of green mass, the cables was changed in 200 m of TL number 25, 3 stands were substituted with new ones at TL number 30.
Lets` noted that, analogical work was carried out at TL number 19. Cable in 160 m lenght was substituted with in order to improve electric power transmission to the refugees living at the objects near the Kur river. Beside it, two transformers by 630 and 400 KVA were changed at Shafa gardeb massif, V. Abdullayev str.
Under other information given by the source, the collective of electric economy of the city are substituted TL supplied inhabitants with electric power of the building number 42 at N. Narimanov str. With SIL type cable lines. TL in 800 m by 6 kV was installed for connecting of TL number 12 and 18 of transformer points, new socket by 6 kV was constructed at one transformer point. New SIL type cable in 260 m distance was installed for the refugees living at the city automobile school.
It should be noted that, 16 transformer points were maintenance repaired, the territory was cleaned of dry grass, 20 disconnectors were constructed, 1,5 transformer oil was added to 15 transformers.