Repair Program of Karelenergo for 2012 Will Amount to RUB 177.8 mln
OREANDA-NEWS. July 18, 2011. Physical characteristics of repair program 2012 of "Karelenergo" higher than the corresponding figures of repair program of current year.
To repair the power grid equipment, “Karelenergo" plans to invest 177.8 million rubles next year.
This is a 12 percent more than plan 2011.
Physical characteristics of repair program 2012 of "Karelenergo" higher than the corresponding figures of repair program of current year. So, next year it is planned to repair 300.7 km of transmission lines of different voltage class, and more attention will be paid to distribution networks - the lines of 6-10 kV.
Also will be continued replacement of cables
Also, to reduce the likelihood of the threat of falling trees, "Karelenergo" conducted operations to clear firebreaks near power lines - next year will be cleared 1344.7 hectares. Under the plan of the repair program, to replace wooden poles will need 1941 cubic meter of wood. In addition, the facility will be replaced 2672 isolators.
In 2012 it is planned to install 58 vacuum circuit breakers intended for switching (on-off operations) of current in electrical facilities. To purchase them will be allocated 21.2 million rubles. This expensive equipment is characterized not only greater reliability, fire and explosion safety, but is simple to design, ease of use, lack of pollution and minimal maintenance.