Eurochem Provides Update on Gremyachinskoe Potash Deposit Development
OREANDA-NEWS. June 23, 2011. EuroChem today provides an update on its Gremyachinskoe potash deposit development. The construction of both cage and skip shafts continues as planned and remains on track to allow potash production to start by late 2013. Above ground, another landmark was reached when the headframes for the two shafts were completed.
Shaft Sinkers (PTY) Ltd., a world leading company in shaft excavation, is sinking and lining the 7 meter-diameter cage shaft. As of early June, sinking operations had successfully passed the first major aquifer and cage shaft lining operations were down to
Prior to the start of sinking operations, housing and sinking headgear, including winch and skip, were erected. Additionally, a warehouse for construction material and equipment was built along with repair shops, an air compressor facility, and a 10/0.525/0.4 kW transformer substation.
The Gremyachinskoe deposit is one of two
More detailed overviews of both projects, including visual updates, are available on the EuroChem website as well as in the 2010 annual report.
Комментарии