IES-Holding Plans to Spend RUR 17.9 bln on Repairs and Re-Equipment
OREANDA-NEWS. June 20, 2011. IES-Holding's Businesses have successfully completed the 2010-2011 autumn-winter period and started preparations for the next heating season. The company plans to invest RUB 17.9 billion in its repair, technical upgrade and re-equipment program.
"The companies of IES-Holding have in general completed the autumn-winter period without major accidents or faults. By results of 2010 investments in current repairs and overhauls, upgrade and re-equipment in IES totaled RUB15.2 billion. In 2011 focus will again be on heat network upgrade", Andrey Vagner, First Deputy General Director, CJSC IES, told reporters.
The repair effort will include planned relaying of heat pipelines with a total length of
The company will continue introducing modern innovative technologies in generating companies and heat networks. For example, it plans to upgrade feeder pumps of two power plants using advanced energy saving technologies imported to
Heat network overhauls and upgrades works are being done with the use of modern insulation materials such as Isoproflex, K-FLEX, flexible foam and some others, ensuring optimal thermal insulation performance and longer pipe endurance. The upgraded pipelines are equipped with remote monitoring systems.