IDGC North-West Starts Construction of Substation "Ida" 35/10 kV
OREANDA-NEWS. May 30, 2011. The costs for the investment project will be about 33 million rubles.
Branch of JSC "IDGC North-West" “Vologdaenergo” began to build a substation "Ida" 35/10 kV in Babushkinsky area (Vologda region). Energy object will be constructed on the base of the old substation which has no the owner. The equipment of the substation is outdated and is in a bad contition.The costs for the investment project will be about 33 million rubles.
On the territory of substation will be constructed the building for the indoor switchgear (ISG) 10 kV and will be installed the cells of 10 kV. In addition, on the base of complete transformer substation 35 kV will be built the outdoor switchgear 35 kV.
Currently on site of the substation 35/10 kV "Ida" started preparatory works.