Mundra Ultra Mega Power Project Achieves Significant Milestone
OREANDA-NEWS. May 30, 2011.
Steam blowing of the boiler is an important activity undertaken prior to commissioning of a new unit or for initiation of turbine powering. Hence, completion of steam blowing is a significant step towards achieving synchronisation of Unit 1 of the Mundra UMPP.
Under this process, steam blows are used to clear / remove any foreign matter / particles / debris and surface scale that have the potential to damage turbine blades during plant operation. Sufficient boiler pressure is maintained to ensure that the piping experiences dynamic pressure to ensure adequate cleaning.
Speaking on the significant development, Alok Kanagat, executive director, CGPL, said, “We are happy to achieve this significant milestone to facilitate commissioning of Unit 1. The completion of steam blowing signifies the readiness of Unit 1 for starting the synchronisation process.”