OGK-5 Successfully Carried out Test Firings of New CCGTs
OREANDA-NEWS. April 5, 2011. Enel OGK-5 successfully carried out the first firing tests of the new combined cycle gas turbines (CCGT) units at its two power plants - Sredneuralskaya GRES and Nevinnomysskaya GRES.
Commenting on the test firings, general director of OJSC “Enel OGK-
The efficiency of two new units is about 58%. The technology used in the construction of the new CCGT allows to significantly improve fuel consumption as well as reduce emissions into the atmosphere.
The construction of the CCGTs at Sredneuralskaya GRES and Nevinnomysskaya GRES, with a gross installed capacity of 410 MW each, started at the end of 2008. Both projects required an overall investment of, approximately, 750 million euros. The CCGT unit at Nevinnomysskaya GRES is expected to become operational by May 2011 and the one at Sredneuralskaya GRES is expected to become operational by July 2011.