Vologdaenergo Will Spend RUB 199 mln for Reconstruction of Substation
OREANDA-NEWS. March 30, 2011. The project implementation will improve the reliability of electricity supply to consumers as well as provide the possibility to connect the additional capacity.
Branch of JSC "IDGC of North-West" “ Vologdaenergo” began to implement an investment project on reconstruction of the substation 110/35/10 kV “Antushevo" in Belozersky District (Vologda region). Capital investment to the project , that is socially significant for the region, amount to about 199 million rubles.
Until the end of 2011 as part of reconstruction grid company will make on-site replacement of existing and install a second power transformers 6.3 MVA, upgrade relay protection and automatics, an automated information-measuring systems for commercial electric power accounting and Automated Systems of Technology Management.
In addition, on the substation “Antushevo" will be held on a complex of works on reconstruction of outdoor switchgear of 110 kV, outdoor switchgear switchgear 35 kV and the construction of the building for operational control center and system of oil receivers and oil collectors.
In accordance with the investment program of "Vologdaenergo”, the substation will be equipped with modern types of electrical equipment.
The project implementation will improve the reliability of electricity supply to consumers as well as provide the possibility to connect the additional capacity.
Комментарии