Gazprom Neft Launches Second Phase of South Priobsky GTPS
OREANDA-NEWS. March 17, 2011. Gazprom Neft has launched the second phase of the South Priobsky Gas Turbine Power Station (GTPS), located in the southern licensed area of the Priobsky deposit (Khanty-Mansyisk Autonomous District). Boris Zilbermints, Gazprom Neft's Deputy CEO for Exploration and Production and Alexander Kim, First Deputy Governor of the Khanty-Mansiysk Autonomous District (Ugra) participated in the ceremony of launching the second phase.
The completion of the facility's construction has allowed the total capacity of the power station to be brought up to 96 megawatts. 4.8 billion rubles were invested into the project, including the costs incurred at the first phase.
The commissioning of the first phase of the power plant allowed Gazpromneft-Khantos to reduce its oil production operational costs. After the commissioning of the second phase of gas turbine power station in the
Boris Zilbermints commented: "The increase in the GTPS's power capacity will fully meet the demand of the energy needed for the development of the
Комментарии