SUEK Will Supply Turbo-Generator Units for Tom-Usinskaya HPP
OREANDA-NEWS. February 18, 2011. OJSC Krasnoyarskenergospetsremont (a subsidiary of SUEK) and OJSC Power Machines have signed an agreement to supply steam turbines and turbo-generators supplied for power stations of OJSC Kuzbassenergo. The equipment is to be delivered as part of investment projects set forth in Power Supply Contracts (PSCs).
The overall amount of the contracts is approximately 4.4bln rubles.
As agreed, OJSC Power Machines is to supply the following equipment:
- KT-115-8,8-2 Steam Turbine for Unit No. 4 at Tom'-Usinskaya GRES in September 2012;
- KT-115-8,8-2 Steam Turbine for Unit No. 5 at Tom'-Usinskaya GRES in June 2013;
- K-225-12,8-3 Steam Turbine and TBB-220-2EУ3 Turbo-Generator for Unit No. 4 at Belovo GRES in September 2012;
- K-225-12,8-3 Steam Turbine and TBB-220-2EУ3 Turbo-Generator for Unit No. 6 at Belovo GRES in June 2013;
"Power Machines and SUEK are good and long-standing partners," said Sergei Mironosetsky, Deputy to General Director of SUEK and CEO of UC Siberian Generating Company. "I believe that our constructive collaboration, precise adherence to the equipment delivery schedule will help the power generating enterprises of SUEK to perform their obligations under the PSCs."
Комментарии