OREANDA-NEWS. February 14, 2011. Under the contract of property insurance against “all risks” and the machines against breakdown, buildings and structures, machinery and equipment, constituting a part of the six branches of OGK-3 OJSC are provided with insurance coverage. The total amount of coverage under the contract amounts 164 billion rubles.

Open Joint Stock Company “Third Generation Company of the Wholesale Electricity Market (OGK-3 OJSC) is a Russian energy company, established as a result of UES of Russia RSC reform. The company consists of six major federal power stations: Kostroma SDPP (installed capacity is equal to 3,600 MW), Pechora SDPP (1,060 MW), D.G. Zhymerin Cherepets SDPP (1,285 MW), Kharanora SDPP (430 MW), Gusinoozersk SDPP (1,100 MW), South Ural SDPP (882 MW). Total installed capacity of OGK-3 is equal to 8,357 MW, and the early production of electric power made 32.13 billion kWh in 2010.