ZTR Will Supply to Siberia 10 Controlled Shunt Reactors
OREANDA-NEWS. February 11, 2011. JSC “Zaporozhtransformator” has signed contracts for delivery of controlled shunt reactors (CSR) for power plants of Siberia region of
According to agreement ZTR will supply for JSC “FSC EES” 10 controlled shunt reactors: 9 single-phase CSR rated for power 60 MVAr, voltage 500 kV are to be installed at substations “Lugovaya” (3 pcs.) and “Ishym” (6 pcs.), one three-phase controlled shunt reactor rated for power 100 MVAr and voltage 220 kV will be manufactured for S/S Demyanskaya.
At present time the advanced payments have been received acc. to all contracts and the order was placed for manufacture. Shipment of equipment is scheduled for the second quarter of 2011.
CSRs manufactured by JSC “ZTR” are purposed for stabilization of voltage and control of overflows of reactive power to backbone and distribution networks.
Since 90-th, JSC “Zaporozhtransformator” has manufactured and shipped 68 units of CSR for Russian Federation, including 16 units dispatched in 2010.