OREANDA-NEWS. February 08, 2011. It is planned that in 2011 in the implementation of the repair program will be invested 204 million rubles.

According to the Department of technical maintenance and repairs of  "Arkhenergo", the actual execution of the repair program last year amounted to 176,068 rubles or 108% of the target.

The increase of actual costs associated with the implementation of emergency repair  activities and unscheduled repair of power facilities.

Last year, "Arkhenergo conducted the capital repair of 1067 km of transmission lines (102% of the plan).
For the year 2010 the company cleared 917 hectares of rides, which is 16% higher than target.

It is planned that in 2011 in the implementation of the repair program will be invested 204 million rubles.