Revenue of IDGC North-West Made RUB 216.5 mln in 9 2010
OREANDA-NEWS. November 22, 2010. 221 km of electric lines and 33.8 MVA of transformer capacity were put in exploitation for the period from January to September 2010.
According to the Department of prospecting development and technological connection of IDGC North-West – the company’s revenue for technological connection during 9 month 2010 is 216,5 mln. Rub. Without VAT
221 km of electric lines and 33.8 MVA of transformer capacity were put in exploitation for the period from January to September 2010 .In 2009 the same parameters were 140,6 km of electric lines and 38,2 МVA of transformers capacity.
The most important projects for technological connection were implemented in Pskov, Novgorod and Archangelsk regions.
In the 3 quarter of 2010 the branch of IDGC North-West “Pskovenergo” has fulfilled the technological connection of production area №4 of “Lugsky abrasive plant with the total capacity 2000 KW.I
In the 2 quarter of 2010 the branch of IDGC North-West “Novgorodenergo” has fulfilled the technological connection of pump station with the total capacity 1630 KW.
In the 2 quarter of 2010 the branch of IDGC North-West “Arkhenergo” has fulfilled the technological connection of the workshops of battery farm ” Vel’skaya” with total capacity 1900 KW.