OREANDA-NEWS. November 22, 2010. 221 km of electric lines and 33.8 MVA of transformer capacity were put in exploitation for the period from January to September 2010.

According to the Department of prospecting development and technological connection of IDGC North-West – the company’s revenue for technological connection during 9 month 2010 is  216,5 mln. Rub. Without VAT

221 km of electric lines and 33.8 MVA of transformer capacity were put in exploitation for the period from January to September 2010 .In 2009 the same parameters were  140,6 km of electric lines and  38,2 МVA of transformers capacity.

The most important projects for technological connection were implemented in Pskov, Novgorod and Archangelsk regions.
In the 3 quarter of 2010  the branch of IDGC North-West “Pskovenergo” has fulfilled  the technological connection of production area №4 of “Lugsky abrasive plant with the total capacity 2000 KW.I
In the 2 quarter of 2010  the branch of IDGC North-West “Novgorodenergo” has fulfilled  the technological connection of pump station  with the total capacity 1630 KW.

In the 2 quarter of 2010  the branch of IDGC North-West “Arkhenergo” has fulfilled  the technological connection of  the workshops of battery farm ” Vel’skaya” with total capacity 1900 KW.