OREANDA-NEWS. October 26, 2010. Specialist started to drill the well for piling to settle the platform of the station that will be the finish point of the railway Adler – “Alpika-Service”. It will be an area of 25 x 300 meters with three pedestrian underground passages.

First of all a complex piling area will be completed. It is necessary to drill 30 meters depth and concrete 500 piles. Drilling is done in severe conditions – on the slope of 45 degrees. Monolith plate of the platform will be assembled afterwards.

Railway station “Alpika-Service” is a complex of interconnected facilities. It includes a mountain part, a breast wall, a platform, and a station. Construction of the station will be completed in 2012. During the Olympic Games 2014 the station capacity will be up to 8,5 thousand people per hour.