IES-Holding Completes Modernizing Perm CHPP-13
OREANDA-NEWS. July 07,
The Garnet Project for reconstruction of Perm CHPP-13 is a part of IES Holding's Diadem investment program. Due to the implementation of this project, the installed electric power capacity of Perm CHPP-13 has almost doubled: from 18 to 34 MW. Thermal power of the new equipment is 19.2 Gcal/hr. The gas turbine unit parameters provide for up to 8,000 operation hours per year, covering basic (summer) heating loads for hot water supply alongside maximum possible electric power production. The new unit's heat production efficiency is 86.9%.
The installation of the new gas turbine unit and all major related infrastructure facilities at CHPP-13 was completed in spring 2009. Pre-commissioning works that lasted for several months included performance tests of all mechanisms, connections, power transmission lines, turbine control assemblies - hundreds of equipment units in total.
The mandatory pre-commissioning test run of GTPP-16PA was completed in November 2009. After the test run and acknowledgement of equipment performance, the System Operator signed a successful test report. All the necessary permits for industrial operation of the gas turbine unit were received in winter 2009/2010.
The gas turbine unit installed at Perm CHPP-13 was developed and produced in
Perm CHPP-13 of the "Generation Urals" Division is located in the city of