IES Proceed with “Malachite” Investment Project Implementation
OREANDA-NEWS. April 1, 2010. “Integrated Energy Systems” proceed with “Malachite” investment project implementation on Perm CHPP-6 expansion. The main building for the new steam-gas plant is being constructed at the power plant site. The total investment volume will make 4,1 billion.
The mounting of the main building for the steam-gas plant with capacity of 124MW has been started at Perm CHPP-6 being a part of IES “Generation of Urals” Division. As of today the load-bearing structures of the new SGP building are assembled. The height of the building which is planned to be constructed within the shortest terms is comparable with 10-storeyed building. In the area where the gas turbines will be located it makes
Other construction works are also actively being performed at CHPP-6 SGP site. They proceed with concrete casting of metalware foundation (
In 2010 IES will assign 4,1 billion rubles to construction of 124MW power generating unit at Perm CHPP-6. The total investment volume into the project which is planned to be completed in 2011 makes 9 billion rubles.
The construction of the steam-gas plant at CHPP-6 site is included into the priority investment program of IES called Diadem. The project is named “Malachite”. The new SGP will be equipped with Siemens equipment. In September 2009 SGT-800 turbines of the latest modification were delivered to the site. The capacity of the power generating unit including two SGT-800 turbines and one steam turbine makes 124 MW, the efficiency is 87%.
“Malachite” project is a key one in