OREANDA-NEWS. March 23, 2010. At the press conference Executive Director of OJSC "Yeniseiskaya ТGC (ТGC-13)" Evgeniy Zhadovets summed up intermediate results of autumn-winter period. By its estimations, despite it is abnormal cold winter, and also work of the equipment with the maximum loading in connection with capacities failures of Sajano-Shushenskaya HYDROELECTRIC POWER STATION, power men of Yeniseiskaya TGC successfully coped with a task – uninterrupted maintenance of consumers with thermal and electric energy.

From November, 2009 till February, 2010 in Krasnoyarsk region and Krasnoyarsk city was keeping stably low temperature of atmospheric air. In January and February, 2010 daily average temperatures of external air fell on 6 degrees below mean annual temperature and at night reached marks lower-40oS. In connection with low temperatures thermal energy issue was increased by all industrial enterprises of Yeniseiskaya ТGC. The maximum volume of thermal energy issue was for the coldest month of a present cold season – January, and equaled 2,501 million Gkal that on 17 % above a similar indicator of the last year. The volume of the electric power development in January reached 1,643 bln kWh that on 27 % more than in January, 2009.

In general 7,620 bln kWh electric power was developed and 10,559 million Gkal of thermal energy was released from the beginning of a cold season before the termination of winter (from September, 17th, till March, 1st, 2010) by the industrial enterprises of OJSC "Yeniseiskaya ТGC (ТGC-13)", located in Krasnoyarsk region and Republic Khakassia.

In connection with failure on Sajano-Shushenskaya HPS YDROELECTRIC, since the autumn of last year and till the present time, all generating capacities of thermal power stations of Siberia, including Yeniseiskaya TGC, work with the greatest possible electric loading.

In connection with long work of the equipment in a mode of the maximum loadings within winter there were equipment failures, mainly the boiler. However they didn't lead notable consequences for consumers because the company had a capacity reserve on the boiler equipment. Besides, as Evgeniy Zhadovets said "Owing to professionalism of the company personnel we have comfort of citizens and reliable work of industrial objects. Their accurate, harmonious work allowed to pass this severe winter without failures. Qualitative carrying out of the winter period is the result of competently planned and conducted repair company of 2009".

Evgenie Zhadovets explained that repair campaign of 2010 which has already been begun, is planned to carry out paying attention to repairs of the boiler equipment. "Replacement of surfaces of coppers heating is provided in times more than in previous years. A main objective of these works is increase of boiler equipment work reliability", - he noted.

Besides, the repair program of Yeniseiskaya TGC in 2010 provides capital, average and operating repair execution of the capital equipment of thermal power stations, (boiler unitы, water-heating coppers, turbine unit, turbo generators, transformers, switches), repair of chimneys, buildings and constructions.

Replacement of pipelines of thermal networks – also one of the major problems for Yeniseiskaya ТGC annually. "Annually the company increases volumes of a rerun of thermal networks. So, in 2007 20,7 km of heating systems in 2008 – 22,0 km, in 2009 - 25,8 km were repaired. We are adjusted that in 2010 we will not lower these indicators", - Evgenie Zhadovets noted. He also underlined that the volume of repair work was planned on the estimation basis of equipment condition and heating systems, and also taking into account the sums put in the tariff for these needs.

Evgeniy Zhadovets noticed that the main problem which can complicate the realisation of the company plans,was still debts of thermal resources consumers. For March, 1st the total amount of delayed accounts receivable equals 2,2 billion rbl. This figure is comparable to expenses for realisation of the company annual repair program: so, in 2009 actual expenses for repair ameasure equled 1,8 bln roubles.