OREANDA-NEWS. December 17, 2009. SOCAR says that well #58 has been commissioned at Gunashli field from additional jacket of Platform #11.

The well with depth of 3 950 m has daily debit of 300,000 cu m of gas and 40 tons of condensate. It became the sixth one at the Platform operating since April 1986.

For the last 23 years the platform was produced 12.4 million tons of oil (together with condensate) and 3.202 bn cu m of gas.

SOCAR also plans to drill another eight wells at the platform that will ensure production of about 500 cu m of gas and 60 tons of condensate per day.