Irkutskenergo Opened New Railway Line and Peredatochnaya Station
OREANDA-NEWS. On 29 June 2009 was announced, that a new railway line and Peredatochnaya station were opened on 23 June, 2009, at Thermal Power Station No.10 controlled by JSC Irkutskenergo
The construction of the railway lines is one of the main goals of the 2009 investment programme launched by the company. Irkutskenergo has invested 439.8m roubles in it with the payback period of about six years.
On 19 June the committee that included the specialists of JSC Irkutskenergo, inspection bodies, the representatives of the Federal Service for Railroad Transport and the representatives of Russian Railroads OJSC (abbreviated as ‘RZhD’ in Russian) signed the resolution to launch the railroad line in permanent operation.
This is the first project that the Company launched during the last twenty years. In 2006 the top management of JSC Irkutskenergo decided that it was necessary to construct its own entrance routes to Thermal Power Station No.10. Due to the opening of a new road the station could abandon the services provided by its reseller – Angara Building Administration OJSC - and to reduce twice the costs for transportation of fuel when preparing for a regular heating season. Irkutskzheldorproject, an
It was originally planned to finish the construction in twenty-two months, but the workers managed to speed up the process and finish their work in fifteen months. The total length of the newly constructed and reconstructed lines is