Sevmash Work Intensity Is Growing
OREANDA-NEWS. On 26 June 2009 was announced, that Drilling rig is assembled on “Prirazlomnaya” platform.
The structure of
This is a final stage of drilling complex construction. Concerning to the platform itself, the progress is very intensive. 59 equipment units shall be installed on the auxiliary module for a week. “Labor intensity increased greatly” – informs S. Rezanov. – First of all, this concerns installation of structures – equipment, electrical panels, traces. A large scope of work is related to piping and ventilation”.
Every day 1500 workers fulfill these tasks, the work is performed in three shifts. But according to the opinion of workers, the construction process is very interesting, responsible and that is very important, well-paid – additional rises are provided at the platform. 2500 specialists are planned to work at “Prirazlomnaya” in the nearest future.