Public Tenders Announced for Lithuanian-Polish Interconnection Project
OREANDA-NEWS. On 25 June 2009 two public procurement tenders were announced in the project for Polish and Lithuanian interconnection: first - consultancy services for preparation of territorial planning and environmental impact assessment (EIA) procedures and documents for the 400 kV overhead power transmission line between Alytus substation – border of the Republic of Poland, second - consultancy services for feasibility study, technical documentation and territorial planning for reconstruction and extension of the Alytus substation with a back-to-back converter station.
The contract winners will to draft a special plan for
The second tender is announced for a feasibility study, technical documentation and territorial planning documents regarding construction of a back-to-back converter station in Alytus and reconstruction of Alytus substation. The winner of this tender will draft a feasibility study regarding Alytus back-to-back converter station and expansion and modernization of the existing TS. The contractor will propose technologies, prepare technical data for procurement documents and perform all necessary works, related to the preparation for design, metering, territorial planning, etc.
“The tenders are performed in compliance with rules of European Bank for Reconstruction and Development, which administers the Ignalina International Decommissioning Support Fund”, - said Mr. Jaroslav Neverovic, Chairman of the Management Board of LitPol Link, in charge of the Lithuanian-Polish interconnection project’s preparatory works.
According to Mr. J. Neverovic, these tenders are open market to players from EU member states,
The deadline for submission of bids regarding the consultancy services for preparation of territorial planning and environmental impact assessment procedures and documents for the power transmission line between Alytus substation – border of the Republic of Poland – July 1, 2009, for consultancy services for feasibility study, technical documentation and territorial planning for reconstruction and extension of the Alytus substation with a back-to-back converter station – July 2, 2009.
Companies, interested in these projects, are invited to apply in writing at the following address: ul. Wojciecha Gorskiego 9, 00-033
Links to tender documents (EBRD website; in English)
Consultancy services for feasibility study, technical documentation and territorial planning for reconstruction and extension of the Alytus substation with a back-to-back converter station
http://www.ebrd.com/oppor/procure/opps/consult/090612c.htm
Consultancy services for preparation of territorial planning and environmental impact assessment (EIA) procedures and documents for the 400 kV overhead power transmission line between Alytus substation – border of the
http://www.ebrd.com/oppor/procure/opps/consult/090612a.htm
Tender documents are also available at the website of Lietuvos Energija AB: