OMZ Signed Contract for Completion of Nuclear Island at Mochovce NPP
OREANDA-NEWS. On 23 June 2009 SKODA JS a.s., a part of OMZ Group, announced that the contract for completion of the nuclear
Out of the four VVER 440-type units originally planned in the Mochovce locality, first two units were put into operation between 1998-1999. For the remaining under-construction and preserved Unit 3 and 4, the crucial part of mechanical supplies was delivered. The plant is a property of Slovenske elektrarne, a.s., whose majority owner became Italian company ENEL in 2006.
For SKODA JS, the supply of key systems for the Mochovce NPP completion project represents a great success that underlines the leading position of the company among Czech suppliers of large investment units. Contraction of this project guarantees development and expansion in the field of nuclear power industry in future years. It will also enable raising up a new generation of specialists, who will subsequently apply their skills and knowledge within the planned construction of new units at Temelin, Bohunice and Dukovany NPP.
Contract value amounts more than CZK 10 billion.
Subject of the supply of SKODA JS a.s.
Technological systems:
Primary circuit
Fuel-handling part
Internal connecting piping
Instrumentation and control system (partially)
Intermediate cooling systems
Servicing workshops
Scope of activities:
Detail design elaboration
Equipment supply and procurement (own production, purchasing)?
Systems installation
Commissioning, tests and setting into operation
Coordination of subcontractors.