Lukoil Assembles Topside on Jacket at Yu.Korchagin Field
OREANDA-NEWS. On 04 June 2009 was announced, that LUKOIL had successfully completed transportation and assembly operations aimed at mounting topside on the jacket of the offshore ice-resistant stationary platform (IRP-2), which is part of the construction facilities at Yu. Korchagin field located in the
As has already been reported, the jacket weighing 1,340 tons was towed to the field, fixed with 15 piles and prepared for the topside to be assembled on it at the beginning of May.
Transportation of the topside to the assembly point started on May, 17, from
The topside comprises living quarters, public and medical premises, a galley, store rooms, ship service systems and other mechanisms, including a helideck and rescue equipment. The living quarters can accommodate 105 people. The platform length is41.5 m, its width is
The platform was constructed by the hardware factory of ООО LUKOIL-Kaliningradmorneft and then, after being knocked down, it was transported by river barges to Astrakhan for complete equipment and coarse assembly at the Astrakhan Shipyard.Later IRP-2 will be connected by a 74.2 transitional bridge with IRP-1 designed for drilling, collection, oil and gas treatment and transportation, which is to be assembled at the field at the end of summer 2009.