IES-Holding Proceeds with Reconstruction of Perm CHPP-6
OREANDA-NEWS. On 21 April 2009 was announced, that Alexander Faustov IES Technical Director has visited IES-Holding “Generation of Urals” Division’s Perm CHPP-6 to get know what the status of power station reconstruction project implementation is.
IES-Holding is executing the top-priority project of power station reconstruction at Perm CHPP-
Along with construction of the combined-cycle plant at Perm CHPP-6 two E-160 steam boilers will be installed. One of the new boilers has been already installed, has passed trial operation and output heat energy into the system of
As of today the designing of the second E-160 steam boiler has been completed. The mounting of the construction has been started. As a result of implementation of IES-Holding priority-driven project due to construction of the combined-cycle plant and two E-160 steam boilers the heat capacity of Perm CHPP-6 will increase by 240 Gcal/hour – up to 833cal/hour by the year 2010.
Perm CHPP-6 is located almost in the center of
During the visit to Perm CHPP-6 Alexander Faustov could see the status of the project implementation straight on the site and noted that it was necessary to make all efforts to introduce the energy capacities in the center of