Turboatom Upgrades Zuevskaya TPP Turbine
OREANDA-NEWS. August 15, 2008. Turboatom OJSC became the successful bidder based on the results of the tender held by energy generating company Vostokenergo for the upgrade of the turbine К-300-240-2 at Zuevskaya TPP power unit No1, the press center of the company reported to UNIAN.
According to the press center, the contract for the upgrade and supply of the equipment is planned to be signed within one week. The value of the contract is about UAH 96 m.
The tender offer assumes replacement of the air-gas channel of the low-pressure cylinders. Turboatom OJSC will manufacture a completely new low-pressure rotor comprising a welded-forged construction and air-gas channel elements. Furthermore, the enterprise will deal with the design, assembly supervision and technical assistance for the startup and debugging procedure.
All this equipment will be manufactured and supplied before the middle of 2009. The upgrade is expected to increase the installed power unit capacity by at least 15 МW, as well as to increase the low-pressure cylinder efficiency to 86%.
Presently, Turboatom OJSC also takes part in the upgrade of ZuTPP unit steam turbine No2. The assembly tasks are scheduled for September, whereas power unit startup is planned in October-November 2008.