OREANDA-NEWS. August 13, 2008. As a whole, branches of the company completed construction of transmission lines of 160.09 km (at the target of 154.88 km). Length of new electric power lines in Komienergo branch is 106.02 km - which is the greatest among other branches. 

According to the investments and capital construction department of IDGC of the North-West, commissioning of new capacities in branches of the company proceeds according to the established action plans. Performance above the plan is observed in a number of branches concerning several positions.

The fastest rates of putting in operation of transmission lines is observed in Novgorodenergo (153 %) and Pskovenergo (158 %) that is 5.05 km and 9.96 km accordingly. For six months of the current year, Arkhenergo actually put in operation 8.68 km of power lines (the target was 6.7 km) that is 130 % of the target. Vologda powermen executed the target by 116%: 26.89 km of new transmission lines were constructed.
 
Komienergo ahead of schedule put into service 0.74 MVA of transformer capacity; they exceeded the target 1.6 times (total capacity commissioned since the beginning of the year is 2 MVA).

As a whole in IDGC of the North-West, the annual indicator of putting of transmission lines in operation was executed by 12 %; as for transformer capacities the indicator was executed by 3 %. The main start-up of power facilities was planned for the 3-4 quarter of the current year.