OREANDA-NEWS. May 23, 2008. "Nizhnekamskneftekhim" INC erected polymerizers at the Polyethylene Facility construction site, reported the press-centre of Nizhnekamskneftekhim.

The site construction and erection work is currently nearing completion.

Major process equipment has been erected, pumps and compressors are being piped, pipelines are under hydraulic test. Start-up of the Facility, 230 Kta PE, is scheduled for Q4 this year.