OREANDA-NEWS. On May 14, 2008 the first of two polymerizers was delivered to the Polyethylene Facility construction site at "Nizhnekamskneftekhim" INC. A unique operation to deliver a so-called "smaller-size" first stage reactor of 152 tons from a cargo terminal to the construction site was implemented by specialists of "Spetstyazhavtotrans" SC Pvt., reported the press-centre of Nizhnekamskneftekhim.

One of these days, it will be installed on the foundation, and a second stage reactor, twice heavier than a smaller one, will be delivered to the Polyethylene Facility construction site.