Stroytransgaz Begins Work on New ESPO Section
OREANDA-NEWS. March 12, 2008. Stroytransgaz recently began construction work on the Mogot-Tynda section of the Eastern Siberia-Pacific Ocean oil pipeline. The contract for the work was signed at the end of 2007.
This section, located along the ESPO route between kilometer 2522 and kilometer 2620, will run 87 kilometers and have a diameter of 1220 mm.
The company has already completed cleanup and preparation of the route along its entire length. Twenty-five kilometers of the pipeline have been welded and a large part of it has been laid into the trench and backfilled.