Troitskaya GRES PP Signed Agreement for Boiler Emulsifiers
OREANDA-NEWS. On 05 March 2008 was announced, subsidiary of JSC “WGK-2” - Troitskaya GRES power plant - signed an agreement for manufacturing and installation of boiler emulsifiers in the boiler and turbine department No.1.
According to the Maintenance General Engineer Deputy Assistant Alexandr Rytanovitch, this type of emulsifier is a modern gas cleaning equipment currently used in small coal-filed boilers.
Emulsifiers proved themselves as the most effective gas cleaning equipment, says Alexandr Victorovich. In compliance with technical requirements the supplier ensures us that after installation suspended particles level of ashes will decrease 5 times! Moreover, installation of new equipment will solve drop entrainment problem.
According to Alexandr Victorovich, this year (in the period from April to November) it is planned to install three boilers in the boiler and turbine department No.1. In the following year the general contractor is obliged to perform the same work for the other boilers in the first selection.
Комментарии