Shimal Reaches High Parameters
OREANDA-NEWS. December 27, 2007. At 400-MVt power station "Shimal" on November of current year was produced about 250 mln. KVt/h of electric power, and it is at 10 mln. KVt/h more than predicted (has been predicted to produce - 240 mln. KVt/h of electric power). The director of station Geisar Bakhishov has informed on it to press-service of joint-stock company "Azerenerji". The director has told, that as a result of carried out repair actions has been reached high parameters. It is necessary to note, that repair works at the station are carried out by local specialists. As he said, in comparison with the similar period of last year on November, 2007 has been produced at 17,8 million KVt/h of electric power more. Within 11 months of 2007 was produced nearby 2 billion KVt/h, and it is produced at 100 mln. KVt/h more than predicted.