04.12.2007, 18:10
Installation of Tihovskaya Substation Completed
OREANDA-NEWS. December 4, 2007. On the electrical substation “Tihovskaya” of the “S.D.Tihov mine” installation work is being over. Erection two high-voltage lines HVL-1 and HVL-2, providing undisturbed operation of the electrical substation is also drawing to a close. Its capacity will be 35 kilovolts. Putting of objects in operation is planned for 15-20th of December, 2007. Specialists of contracting public corporation “Kuzbassenergoremont” work on the electrical substation and the high-voltage lines. Now they are building free-flow conduit. Work is planned to be over on the 10th of January, 2008.
Комментарии