Subtration “Martush” of JSC “Sverdlovenergo” Was Installed
OREANDA-NEWS. October 17, 2007. The second pressure transformer with capacity10 Mw was installed at substation “Martush” 110 kW in Kamensk-Uralskiy.
Works for reconstruction of “Martush” substation are maintained according to the investment program by JSC “Sverdlovenergo” and were started in June 2007. More than 52 mn out of the total sum meant for investment program and equal to 72,5 mn have been already applied. At the present moment there was finished installation work of open switch gear 110 kW and equipment of standard switch gear 10 kW. There were also installed 2 modern electro-gas switching gears.
Installation of new transformer will help to satisfy the demand in power capacity and energy for cottage area in Martush village, recreation center in Brod village, silicate sand cast of CJSC “Simat” as well as residents of new district “Uzhny” in Kamensk-Uralskyi.
Besides there should be installed tie-breaker 110 kW at the substation which will provide more reliable feed circuit in both work and repair regimes.
Комментарии