JSC “Sverdlovenergo” for 2007 Finished in Serovsk Power Networks
OREANDA-NEWS. For the present moment works to install additional current protection have been finished at Ivdel and Gari substations. Equipment of additional current protection should be delivered and installed at Konzhak substation in October this year.
Works on installation of arc protection of “Photon” type (for the present day equipment installation has been already done) are on its final stage at Gari and Atymja subsubstations. In October-November it’s planned to install equipment at substations Kurdyukovo and Puksinka.
Soon there will be finished works to install accident recording system at Predturje substation.
Works on installment of control current management apparatus at Andrushino and Snezhnaya substations are planned to be started in November.
Thanks to installment of relay protection and automatics equipment, reliability of work and power supply should improve significantly.