JSC IDGC of the Center Invested More than RUR 471.2 Million
OREANDA-NEWS. August 6, 2007. According to the results of the 1 half of 2007 the planned repair program was accomplished in the dependent grid companies.
35-110 kV and 0.4-10 kV (kilovolts) power transmission lines were fully repaired. More than 1 914.8 km of 35-110 kV lines and more than 7 077.2 km of 0.4-10 kV lines were repaired in total. 93 35-110 kV transformer substations and 2 543 6-10/0.4 kV substations were also repaired in the 1 half of the year.
More than 4 446 hectares of glades including 2 092.7 hectares of glades for 35-110 kV lines and 2 353.3 hectares of glades for 6-10 kV lines were cleared in the 1 half of the year.
JSC IDGC of the Center invested more than 471.2 million rubles in the repair program in the 1 half of 2007, including 61.1 million rubles to repair 35-110 kV PTL, 74.5 million rubles to repair the equipment of 35-110 kV substations, 199.8 million rubles to repair 0.4-20 kV power grids, and 47.2 million rubles to clear glades of 6-110 kV lines.
The information is provided on the web-site of JSC IDGC of the Center.
Комментарии