OREANDA-NEWS. The Board of OJSC “Mosenergo” has discussed results of the industrial-economic and financial and economic activity of the company for 2006, and also problems for 2007.

In 2006, power stations of the company made 64 378 million kWh electric power and 70 181 thousand Gcal of thermal energy. The gain of maximum loadings has made 4,5 %.

In 2006, the net profit of the company has made 1,524 billion roubles.

In 2006, OJSC “Mosenergo” commissioned 166,2 MW new capacities due to replacement of the turbine 25 MW at HPP-1, input of the gas turbine with capacity 31,2 MW at GTU-TEC in Electrostal and replacements of a turbine unit 110 MW at TPP-21.