200 Thousand Tons of Large Diameter Pipes to Be Delivered to ESPO by Viksa Metallurgical Works
OREANDA-NEWS. JSC “VMW” will deliver up to 200 thou tons of large diameter pipes for Transneft to build East Siberia – Pacific Ocean pipeline system.
In February, the works began manufacture and deliver of 1220 mm pipes with antirust coating. Over the month, it is expected to deliver about 13 thou tones of pipes 19 and 22 mm wall thickness.
Besides, deliver of pipes of 1067 in diameter and 14,17,20,21 and 25 mm wall thickness is going on.
The first consignment of pipes for ESPO was delivered in December 2005. From the very beginning of participation the project the pant delivered about 200 thousand tons of pipes 1067 mm in diameter.