Lydian International looks to undertake intensive exploration drilling
Situated next to the main north-south road corridor of Armenia, Stevenson explained how Lydian geologists made the chance discovery of the Amulsar project, when they took a rest stop next to the road more than a decade ago.
Amulsar is a true greenfield discovery. Although the alteration had been mapped in early Soviet times for a silica resource and, later Soviet exploration had been carried out for silica, gold was not reported until a reconnaissance trip by Lydian geologists in 2005 recognised the potential for epithermal-style gold mineralisation in rocks beside the highway.
“Geologists have been driving past the mountain for years without ever thinking to explore for gold. Then our guys decided to climb the mountain and their prospecting resulted in the multimillion-ounce Amulsar discovery – a project 100%-owned by Lydian with no underlying royalties except for taxes to the government,” he explained.
The company immediately staked claims on the property and launched intensive geologic investigations. Lydian has established that gold, hematite and silica occur within fractures, narrow oxide-filled breccia zones, and a few larger hydrothermal breccia zones.
Fast forward to a positive construction decision in 2015 – subject to financing – Stevenson laid bare the difficulties of obtaining development bankrolling at a time when the market was in the grip of the historic commodity downturn.
“By the end of 2015, traditional sources of financing just dried up. As a result, and with our debt-to-equity ratio also working against us, it prompted us to seek a nontraditional debt-equity stream funding solution through Orion Mine FinanceManagement and Resource Capital Fund,” he said.
The financing plan provides $370-million for project construction costs and other estimated interest costs, financing fees and corporate expenditures during construction. Lydian completed its comprehensive financing plan with the closing of the $50-million ING Bank term facility in February, to fund crushing, conveying and electrical equipment, part of a $85-million equipmentfinancing in which Caterpillar and Ameriabank also participated.
Stevenson pointed out that Amulsar will become Armenia’s single largest gold mine once in production, and contribute significantly to the economy.
Based on compliant proven and probable reserves of 102.7-million tonnes grading 0.79 g/t gold, for 2.6-million ounces of contained yellow metal and 12.72-million ounces of silver at a grade of 3.85 g/t, Amulsar is expected to have an initial mine life of ten years.
Yearly gold output is expected to average 225 000 oz, at low all-in sustaining costs (AISC) of $579/oz. Amulsar will process 10.2-million tonnes of ore a year, with gold recovery targeted at 87.2%.
Contributing to the low AISC is the fact that loaded haul trucks will travel downhill from the 2 800-m-high-mountain-ridge openpit mine, to the mill, from where gravity transports the ore on a conveyor belt to the conventional heap leach pad. Stevenson pointed out that the conveyor system is expected to generate enough electricity to power the mill as a key feature.
Another positive for Amulsar is the fact that it is a large-scale oxide deposit, entirely amenable to cheap heap leach processing.
The project has an after-tax net present value, at a 5% discount, of $494-million, and an internal rate of return of 29%. The mine plan is based on a gold price of $1 150/oz and $16/oz of silver.
“Amulsar will have a significant impact on the Armenian economy,” Stevenson stressed. Mining accounts for about 10% of the nation’s gross domestic product, and Amulsar is singly expected to contribute up to about 25% of that number, once in operation.
The mine will be among the top five revenue earners for the Armenian government, contributing between $40-million and $50-million in taxes each year. It will sustain about 700 permanent jobs in the local economy once operational.
Another critical feature working in Amulsar’s favour is the fact that it enjoys strong governmental and local community support, with Stevenson describing the comprehensive social permitting programme as being “very rewarding”.
During the first quarter ended March, construction at Lydian’s Amulsar project continued to progress, with the completion of the financing package, ordering key equipment, starting fabrication and expanding earthworks just as spring conditions opened working faces. Constructionof worker accommodations and advancing major bid packages for contracts to be awarded during the current quarter also enjoyed significant attention in recent weeks.
Stevenson noted that field activities were somewhat limited during the early part of the first quarter, but ramped up as planned during March. Work is now advancing to higher elevations with project activities expected to peak during the second and third quarters.
Winter conditions and minor delays in completing several contracts slightly impacted the project schedule.